PROJECTS / WATER

Plaines Wilhems District-2014

100km Sewer network & House connections

Forming part of the Plaines Wilhems Sewerage Project Stage 1, the Project objective was to connect a maximum of existing properties in the region of Central, North East and South West Quatre Bornes to a new sewerage network. Carried out in JV with Chinese engineering company BCEG, the work comprised construction of approximately 100,000m of street sewers together with the survey and design and construction of 12,000 new sewer house connections. The work also required the replacement of about 47,000m of existing outdated CWA water supply pipelines.

  • Project Title

    PROJECT TITLE

    Plaines Wilhems Sewerage Project – Stage 1. Contract WW99F: Construction of Reticulation Network and House Connections – Lot 2
    Internal reference: STC401

  • Project Facts

    PROJECT FACTS

    Project Duration: 72 months
    Contract Value: Rs 2,5 Billion
    DI pipes: 7200m
    Pipes: 100,000 m
    CWA pipes 40,000m
    House Connections: 12000 no
    Reinstatement: 275000 m2

  • Challenges

    CHALLENGES

    Construction of sewers in confined, narrow roads under traffic and with multiple existing services.
    House connections in very restricted back yards and alleyways.

  • Client Team

    CLIENT TEAM

    Employer: WMA
    Project Manager: WMA
    Engineer: Lotti & Associati

    SOTRAVIC TEAM

    CM: Sheik Varsally
    PM: Dinesh Ganasee